Power Transmission Transformers

Our oil-type transformers are essential for power supply and distribution systems in industrial, mining, and civil buildings. They offer flexible installation options and perform reliably in various environmental conditions and altitudes. Visit our factory store for free tours, support bulk ordering, and maintain inventory for quick delivery.

Product Details

Oil-immersed transformers should pay special attention to their fire safety measures.

1. The fire separation distance between oil-immersed transformers with an oil content of more than 2500kg and oil-filled electrical equipment with an oil content of 600kg-2500kg should not be less than 5m.

2. When the fire separation distance between two adjacent oil-immersed transformers does not meet the requirements, a fire partition wall should be installed or a fireproof water curtain should be added to the top of the fire partition wall. Only fireproof partition walls or fireproof water curtains can be installed between single-phase oil-immersed transformers.

3. When the distance between the outer wall of the factory building and the outer edge of the outdoor oil-immersed transformer is less than that specified in the specification table, a firewall should be used for the outer wall. The distance between this wall and the outer edge of the transformer should not be less than 0.8m.

4. When the outer wall of the factory building is within 5m from the outer edge of the oil-immersed transformer, no doors, windows or holes should be opened below the horizontal line of the total thickness of the transformer plus 3m and within the range of the outer edges on both sides plus 3m; no doors, windows or holes should be opened outside this range. The fire resistance rating of doors and fixed windows on fireproof walls shall not be less than 0.9h.

5. When the oil volume of an oil-immersed transformer and other oil-filled electrical equipment exceeds 1000Kg per unit, an oil storage pit and a public oil collection pool should be set up, and transformer pebbles should be placed for fire prevention and oil unloading.

6. Oil-immersed transformers should be equipped with fixed water spray and other fire extinguishing systems in accordance with current relevant regulations. Oil-immersed factory transformers should be installed in a separate room. The door of the room should be a Class B fire door that opens outwards and leads directly to the outside of the house or corridor, and should not open to other rooms.


Single Phase Oil Immersed Power Transformer 1000kva

Industry-Specific Attributes

UsePower
PhaseSingle
Coil StructureTOROIDAL
Coil NumberAUTOTRANSFORMER


Other Attributes


Place of OriginShandong, China
Brand NameJinshida
Model NumberSCB11-30~1600/,S11-30~1600/,S11-30~20000/35
Product nameOil Immersed Power Transformer
Frequency50Hz/60Hz
Rated capacity400kVA
StandardISO9001: 2008
NameOil Immersed Distribusion Transformer
Rated voltage22KV
Warranty24 Months
Cooling MethodONAN
Capacity400kva
Transformer typeS11 Oil-immersed Transformer


Packaging and Delivery

Selling Units


Single item


Single package size


1260X820X1240 cm


Single gross weight


50.000 kg


Product Paramenters

10 Rated Power (kVA)

High Voltage (kv)

Low Voltage (kv)

Connection symbol

No-load loss(W)

On-load loss(W)

No load current (%)

30KVA

6.3KV

15KV

22KV

25KV

33KV

10KV

11KV

20KV

35KV

 

0.4

Ydn11

Yyno

570

4300

0.4

50KVA

80KVA

680

5140

0.45

100KVA

125KVA

810

30800

0.4

160KVA

200KVA

980

7500

0.4

250KVA

315KVA

1150

10300

0.35

400KVA

500KVA

1360

12000

0.3

630KVA

800KVA

1640

145000

0.6

1000KVA

1250KAV

1950

19140

0.6

1600KVA

2000KVA

2340

22220

0.5

2500KAV


Customized Various Models


various models

various models



Product Process


product process

Application

Our products can be used in the power industry, mining industry, aviation industry, petroleum industry, bridge engineering, etc.

application



Certificate

certificate


Packing and Delivery


packing and delivery

The operating voltage of the power transformer should generally not be higher than 105% of the operating tap voltage, and shall not exceed the maximum operating voltage of the system. For special use cases, operation at no more than 110% of the rated voltage is allowed.

The top oil temperature of oil-immersed transformers should not exceed operating procedures or manufacturer's specifications. For forced oil circulation water-cooled transformers, the top oil temperature should generally not exceed 700°C.

Transformers with strong oil circulation cooling should be able to control the cooling operation according to temperature and/or load.

When a transformer is put into operation, the indications of the instrument should be constantly monitored and the operation status of the transformer should be grasped in a timely manner. If defects or abnormalities are found, measures should be taken to eliminate them promptly. If it cannot be eliminated at that time, surveillance must be strengthened. Prevent the expansion of accidents. and determine countermeasures as soon as possible.



Company Profile


Our Advantages

1.Quality Assurance

Jinshida follows the standard of customer demand, providing technical support and full quality control supervision to ensure that our products have excellent quality and reliability.

2.After-sales guarantee

Jinshida provides global customers with worry-free after-sales service, at three-year warranty period to allow customers to enjoy long-term stability of performance, to ensure that customers in the process of use can be satisfied with the experience.

3.Delivery time guarantee

Jinshida strictly adheres to the contractual delivery date to ensure that customers can receive the required products on time.


FAQ

1.On site/on line Production and Quality production supervision.Customer own the product supervision right, and for each important process during the manufacturing and testing (or to be defined by customer's request), by means of on site check or on line check. Meanwhile, we also provide traceable records for check.

2.Packing&Transportation

Wooden pallet packing or or to be defined by customer.

3. Leading time

For standard product, approximately 15 working days before delivery.

For customized product, approximately 20~30 working days before delivery.

Order quantity/customization requirements can also affect the leading time.

4.Warranty/ Payment terms

2 years of warranty at least.For the first order we normally accept T/T, 30%+70%. Regular customer payment terms to be negotiated by both parties.


jsd




Leave your messages

Related Products

x

Popular products

x
x